Saturday, January 15, 2011

Sumadhura Sawan - Status@Jan

Hi,
Last year was really hectic. Had been upto many tasks. But it really brought me happiness to book my own flat. Since my office is near to the apartment site, I had been really on my toes to keep myself updated with the developments. Here are a few:
1) Work is going on at a proper pace for the SAWAN project.
SJR unity project, <1km to the Sumadhura SAWAN project which had started bookings on Feb 2010 has less construction done as compared to the SAWAN project which started bookings in Dec 2010.
2) The Euro school has become operational. It is located just next to the Sumadhura SAWAN project. The road leading to the EURO school project needs to be improved.
3) The construction for the basements are in shape now. We can get a clear picture of the basic plan.
4) The BBMP approval is pending. Though Sumadhura has attained the approval of the other parallel projects , but as yet the approval for our project is pending. They will be getting it by January end is what they say.

Also in the process of making people known to each other I have been able to connect to the following people who have booked flats in the project:
Chinmoy Pattanayak
Pallanti S Rao
Nihar Rajan Mallick
Deepak Patro

Will keep you all posted and updated.
Thanks.